TABLES AND CHARTS, INFORMATIONS

Hydro power plant Djerdap 3 is planned for constructionUpgrading of the existing three hydro power plants on the river Drim
Installed power 2,400 MW Installed power 500 MW
 Installed flow is 400 m³/sInstalled flow is 200 m³/s
Serves for quarterly equalization of electricity in SerbiaServes for annual equalization of electricity in Albania
Uses the Danube River for water abstraction, additionally builds 2 artificial lakes that do not have running water from the riverUses Skadar Lake for water abstraction, uses already built 3 artificial lakes that have running water from the river
The total capacity of the reservoir is 578,000,000 m³ of waterThe capacity of part of one reservoir is 1,100,000,000 m³ of water
Ratio of accumulated water for installed 1 MW = 241,000 m³ of waterRatio of accumulated water for installed 1 MW = 2,200,000 m³ of water and more
The cost of construction is 6,000,000,000 eurosThe cost of construction is 500,000,000 euros
Construction time 6 to 10 years in stagesConstruction time 2 years
The time limit for the placement of capital is three times longer than the innovative method of constructionThe time limit for the placement of capital is three times shorter compared to the classic method of construction